logo
call
Bridges hero

Bridges

Bridges connect two things that behave differently underground: a structure on deep pile foundations that doesn't settle, and an approach roadway on ordinary fill that does.

Solutions for this Industry

Bridge Approach Settlementarrowactive arrow

Infrastructure Settlement Controlarrowactive arrow

Loose Sandsarrowactive arrow

Sibling Industries

Highwaysarrowactive arrow

Rail Systemsarrowactive arrow

Airportsarrowactive arrow

Tunnelsarrowactive arrow

Need a Site Assessment?

call icon

800-240-7868

Smiling woman in a yellow hard hat and suit jacket points up, holding blueprints.

Bridges connect two things that behave differently underground: a structure on deep pile foundations that doesn't settle, and an approach roadway on ordinary fill that does. That gap, along with abutment soils exposed to scour, erosion, and decades of traffic vibration, is where most bridge ground-engineering problems start. Departments of transportation and bridge authorities turn to ground stabilization when an approach, departure, or abutment needs to be fixed without taking the structure fully out of service.

Bridges feature

Bridges Industry Challenges

Bridge infrastructure carries pressures that don't apply the same way to an open stretch of highway.

White checkmark symbol within a bright red circular background, indicating completion or success.

Settlement at the bridge approach and departure slabs, "the bump at the bridge," creating unsafe transitions at highway speeds

White checkmark symbol within a bright red circular background, indicating completion or success.

Erosion and scour around bridge abutments and piers following heavy rain, seasonal storms, or flooding

White checkmark symbol within a bright red circular background, indicating completion or success.

Loose sand, gravel, or subsurface voids around abutments loosening over decades of load and vibration

White checkmark symbol within a bright red circular background, indicating completion or success.

Traffic control and lane closures adding cost and disruption to any repair requiring excavation near an active structure

White checkmark symbol within a bright red circular background, indicating completion or success.

Meeting a state DOT's own bridge inspection ratings and structural standards before a repair is accepted

Bridges challenges

Benefits of Bridges Solutions

Bridge infrastructure demands a fix that restores the transition and the abutment without taking the structure out of service.

White checkmark symbol within a bright red circular background, indicating completion or success.

Keeps the bridge open. On the Sault Sainte Marie International Bridge, injections were applied entirely from the top of the bridge, completing repairs on both sides in only two days

White checkmark symbol within a bright red circular background, indicating completion or success.

Engineered to the state DOT's own requirements. On an NCDOT rehabilitation project in Charlotte, North Carolina, UDI was applied according to a site-specific injection plan to restore settled approach and departure slabs to their originally designed grade

White checkmark symbol within a bright red circular background, indicating completion or success.

Restores the approach slab and stabilizes abutment soils directly, rather than patching the visible symptom above them

White checkmark symbol within a bright red circular background, indicating completion or success.

Often well under budget. A bridge settlement project in Binghamton, New York was completed 60 percent under budget compared to the original estimate

How Our Process Works

1

Investigation

Approach slab and abutment conditions are evaluated through inspection and testing before any repair plan is designed.

2

Planning

Injection design and sequencing are developed around the specific bridge's structure and the state DOT's own requirements.

3

Access

Small-diameter injection points are installed with minimal lane closures or disruption to the bridge itself.

4

Injection

Expanding polymer is placed to stabilize abutment soils or lift settled approach pavement as needed.

5

Monitoring

Real-time tracking confirms precise alignment and grade during the lift.

6

Validation

Final inspection confirms ride quality and compliance with the state DOT's own standards.

Frequently Asked Questions

As part of an NCDOT rehabilitation project on I-277 in Charlotte, North Carolina, UDI was applied according to a site-specific injection plan and successfully restored each identified settled bridge approach and departure slab to its originally designed grade.

On the Sault Sainte Marie International Bridge, injections were applied entirely from the top of the bridge to stabilize sub-surface sand, gravel, and rock in and around the abutments, without needing to access them from below.

Often significantly so. A bridge settlement project in Binghamton, New York was completed 60 percent under budget compared to the original estimate.

Yes, in most cases. Both sides of the Sault Sainte Marie International Bridge were repaired in only two days, and a bridge lifting operation in Buffalo, New York used a grid injection pattern to restore the roadway to grade without an extended closure.

A bridge structure typically sits on deep pile foundations that don't settle, while the approach roadway sits on ordinary fill that does. In North Carolina, excessive rain, seasonal storms, and flooding regularly weaken the soils supporting bridge approaches, departures, and slopes, which is exactly the kind of gap that opens between the two.

Stabilize Critical Bridge Infrastructure

Get an expert site assessment and a tailored stabilization plan.

Request a Site Assessment

URETEK

Ground improvement solutions engineered for performance.

Contact Us

Find Local Experts

Phone
Address

13900 Humble Road, Tomball, TX 77375


Privacy PolicyTerms of ServiceSitemap
linkedin iconfacebook icon

© 2026 Uretek. All rights reserved